Telstra Outage Description

At 18:45:00 on 23rd October, a maintenance window was used to make enhancements to the current UPS equipment on the 3rd floor of Telstra’s London Hosting Center. This work resulted in the total loss of power on the 3rd floor co-location facility.

A thorough Method Statement and Risk assessment had been carried out to make sure all switching was correct and the load would be smoothly transferred through the static switch to raw mains for the duration of the maintenance. Telstra are unable to access this particular breaker and so could not predict that it would fail under a load well below its capacity. The Thermal and Ultrasonic survey of the electrical infrastructure carried out recently showed normal operation.

The activity being undertaken in the maintenance window was to temporarily move the load from one leg to another. This would allow Telstra to undertake works to enhance the current UPS equipment. The load in the 3rd floor co-location facility is currently under 1250 amps. This load is fed by two feeders rated at 1250 amps each. The schematic below shows the basic configuration of the power layout.

In order to conduct the maintenance on the UPS the load needed to be swapped on one leg thus allowing the Static Bypass Switch to throw and in turn allowing Telstra to move the load back but with the UPS isolated ready for safe working.

When the load was moved a Breaker rated at 1250amps failed. This is the root cause of the issue, as already mentioned to total load was under 1250 amps and should have been easily supported by this breaker.

The power outage started at 18:45:10 and power was restored at 18:47:05. As a direct result all services within the 3rd floor co-location facility powered down.

As soon as the breaker tripped, we immediately isolated the UPS’s and static switch, reset the breaker and put level 3 into wrap round bypass supply. This keeps the UPS and static switch out of the circuit and supplies the load on raw mains.

As the load is well below the capacity of the breaker, it was assumed the breaker had tripped early. At the time Telstra had no way of safely checking this breaker without switching the power off. Telstra engineers took the decision to remain on raw mains until further investigations and preparations could be made.

On Friday 24th October, Telstra arranged for a Metropolitan Electrical Tegg service team to attend site with all the necessary H&S equipment for them to remove the cover and check the breaker whilst it is live. Telstra will be better placed to make a decision on the best way forward once these findings have been collected and assessed.

Telstra Remedial Action

The most appropriate actions will be determined as soon as Telstra are given the findings of the specialist report.

Clearly, Telstra needs to migrate back on to UPS supply as soon as possible. Based on the outcome of the analysis of the breaker Telstra will be looking to undertake an emergency planned outage at 00:00 Sunday morning.

This document provides a high level report of the events, highlights areas of concern and lays forth remedial steps, which are being put in place to prevent the same type of episode arising in the future. Telstra would like to offer its sincere apologies for the unforeseen disruption caused to our customers. All teams involved are working together to prevent this situation arising again.